A key milestone was reached on Friday 12th February with successful completion of the foundations. This has allowed the structural steel frame to commence on Monday 22nd February. The steel frame will take approximately 6 weeks to erect and we anticipate completion around easter time. We now have visibility of the project above ground which on completion allows multiple work faces to progress during April and May.
Latest News / News
Structural Steel Frame – Deluna House, Oldham Road, Manchester, M4 5FE
published
February 24th, 2021