Following demolition of the former Cheshire Cheese Public House in September 2020 works on the new build apartment scheme commenced in earnest as planned at the end of October 2020.
The site was cleared of below ground obstructions, the former public House basement filled and during November the CFA pile installed. The overall construction programme is 60 weeks with us currently being in week 13 and a scheduled completion of December 2021. On returning from the Christmas holidays we have installed below ground drainage systems and have now moved to preparation of the CFA piles in readiness to receive the foundation pile caps and ground beams. The superstructure steel frame is planned to begin in the first few weeks of February 2021.