February 24th, 2021

A key milestone was reached on Friday 12th February with successful completion of the foundations. This has  allowed the structural steel frame to commence on Monday 22nd February. The steel frame will take approximately 6 weeks to erect and we anticipate completion around easter time. We now have visibility of the project above ground which on completion allows multiple work faces to progress during April and May.